Shop Floor - Order of steps in Work Orders
Enabling strict sequential order for both operations and steps when dependencies are activated, if Dependency is unchecked, operators retain the flexibility to perform steps within each operation in any order.
Shop Floor - Order of steps in Work Orders
Enabling strict sequential order for both operations and steps when dependencies are activated, if Dependency is unchecked, operators retain the flexibility to perform steps within each operation in any order.
STORY BEHIND THE FEATURE
ODOO BEHAVIOR
CLUEDOO BEHAVIOR
With Cluedoo’s enhanced Work Order Dependencies feature, activating this setting enforces a strict sequential order both for operations and for the steps within each operation (e.g., completing step 1 before moving to step 2 or 3). However, if Dependency is unchecked, operators retain the flexibility to perform steps within each operation in any order, allowing for adaptable workflows when a strict sequence is unnecessary.
MODULE +
CLUEDOO RECOMMENDATIONS
Install on 100% of the database.
HOW TO USE THIS MODULE
1. Go to Settings > Tick Work Order Dependencies under Work Orders > Save | |
2. Go to Manufacturing > Products > Bills of Materials > New to create a new BOM or choose an existing one > Miscellaneous > Tick Check Dependency | |
3. Under Operations, fill in the necessary information > Save | |
4. Fill in the steps in the Instructions > Save | |
5. Head to Manufacturing > Operations > Manufacturing Orders > New > Select Product > BOM and Work Orders should be automatically added > Confirm | |
6. Open Shop Floor with the circle button or open Shop Floor via Work Order (blue button) | |
7. If you do step 2 first, a warning will raise, indicating that you have not done step 1 before doing step 2. If you want to continue, you need to do step 1 before step 2. |